TrackerDevelopment11 min read

The 10 Acres Across From King Soopers on Ridge Road in Castle Rock: What Council Annexes on Election Night, 54,000 Square Feet, One Drive-Through, and No Renewable Water Required

RidgeView Town Center passed first reading 7-0 on Oct. 20 with nobody in the room to speak on it, and gets its final vote Nov. 3 while the town is counting ballots. It is not a subdivision: zero homes, a required sit-down restaurant, a 25-foot height cap, and a water deal that lets the owner skip the renewable-water rule because the lot is infill. The Town's own analysis says it nets between $53,000 and $453,000 a year, depending on who leases the space.

By Discover DougCo Editorial Team·

This is the second of our development trackers. The first covered the west side of Castle Rock, where the interchange and the Costco are. This one covers 10 acres on the east side that most people drive past on the way to King Soopers, because the town is about to annex them on the night of the election, and because the file explains more about how Castle Rock grows than its size suggests.

On Oct. 20 the Town Council approved the RidgeView Town Center annexation, its zoning and its development agreement on first reading, each 7-0, with no public comment. The second and final readings are set for Tuesday, Nov. 3, which is Election Day; council's regular start is 6 p.m., an hour before the polls close, though the agenda had not been posted as of Thursday. We read the staff reports, the development agreement, the Town's fiscal impact analysis, the eligibility file, the neighborhood meeting summaries and the one letter the public sent. Here is what the town is agreeing to.

What it is, and what it is not

The name suggests a town center. The plan is a commercial pad. The zoning staff report sets a maximum of 54,000 square feet of non-residential space in two planning areas: PA-1, 1.74 acres at the south end, where one restaurant with a drive-through is allowed, and PA-2, 6.23 acres covering the rest, where drive-throughs are prohibited and the permitted list is office, retail, restaurant, clinic and personal services. The one hard requirement is a full-service restaurant of at least 6,000 square feet, which the zoning defines as a place where "customers are seated by waitstaff." The applicant told the September neighborhood meeting it wants "a niche restaurant" rather than a national chain and has no tenants yet; in 2023 the comparison offered was "a stand-alone, sit down restaurant such as La Loma."

What is prohibited is as telling as what is allowed: gas stations, car washes and auto repair, storage, kennels and animal day care, marijuana businesses, and drug, alcohol or substance-abuse treatment clinics. There are no homes. "No residential uses are included," the staff report says, and the Town's fiscal analysis is built on the project being "entirely nonresidential."

54,000

square feet, maximum

6,000

square feet of sit-down restaurant, minimum

1

drive-through allowed, in the south 1.74 acres only

25

feet, the height cap under the Moderate Skyline rule

2.21

acres of open space, 21 percent of the site

7-0

the first-reading votes, Oct. 20

The site shapes the rest. The northwest corner sits in the town's Major Skyline area, where structures are prohibited and the rock outcroppings stay as they are; the rest is Moderate Skyline with a 25-foot cap, and buildings sit 35 feet back from Ridge Road. The April 2024 land suitability report found 20 to 50 percent rock slopes in the southwest corner, rockfall potential and expansive soils, and no wetlands or listed species. The one full access is a signalized intersection aligned with the King Soopers driveway across Ridge Road, plus an emergency-only access at the south end. The west edge, 2.21 acres along the rock, is dedicated to the Town as open space with a natural-surface trail the developer builds, stubbed toward the property behind it. That property matters: the Memmen-Young planned development to the west is already zoned for up to 1,035 single-family homes and has not been built. RidgeView's trail is designed to connect to a neighborhood that does not exist yet.

The water

Castle Rock's growth argument is a water argument, so this is the section to read. The development agreement requires the owner, at annexation, to convey all of the property's groundwater rights to the Town by deed: 17.22 acre-feet a year. The Town's title review found 14.8 acre-feet of that creditable, which converts to a water credit of 13.5 single-family equivalents, the Town's unit for demand. The Town estimates the project as proposed needs 43.85 SFE. The roughly 30-SFE gap is covered one of two ways: the owner buys Town-held off-site groundwater at the non-residential rate of $2,270 per SFE, first come first served and at the Town's discretion, or, if the Town has none to sell, acquires and conveys off-site groundwater rights on its own. At the Town's rate, 30 SFE is on the order of $68,000; that arithmetic is ours, not the agreement's. The existing well stays in domestic use until the first construction permit, then is abandoned at the owner's cost.

Then the sentence that defines the deal. The agreement states that "the Project is considered 'Infill' under the Water Plan and, therefore, Owner is exempt from the requirement to provide renewable water" under section 4.04.045.B of the Town code. Castle Rock's 2030 comprehensive plan lists, among its annexation criteria, that a project "secures renewable water to 100 percent of the expected development." The annexation staff report walks through that criterion and answers it with the infill exemption: the lot is surrounded by town, the pipes are already in Ridge Road from the widening, so the renewable-water dedication the plan contemplates does not apply. The owner still pays the Town's uniform development fees, which the agreement defines to include renewable water resource fees and system development fees, and still reimburses the Town $75,768.84 for the two 12-inch main stubs it installed during the road project. Castle Rock Water reviewed and approved the plan, the utility report and the drainage report. The result is a commercial project that adds about 30 SFE of demand to the Town's system on groundwater, bought or conveyed, with no renewable supply attached to it. That is the policy the code allows for infill; it is also the thing residents who follow the water plan will want to know was decided.

The money

The Finance Department's fiscal impact analysis, final as of Oct. 2, models three tenant mixes against the same 54,000-square-foot envelope, because, as it says, tenants are "the primary driver" and none are signed. The base case assumes 6,000 square feet of restaurant, 30,000 of retail, 12,000 of office or medical and 6,000 of recreation or service. It counts only half of restaurant and retail sales as new to Castle Rock rather than shifted from existing businesses, assigns no direct taxable sales to the office, medical and service space, and uses the Town's 4.2 percent sales tax, the 0.92 mill levy and a 25 percent commercial assessment rate.

Estimated annual net fiscal impact to the Town, by tenant scenario (Castle Rock Finance, Oct. 2, 2026)
Retail-oriented453 thousand dollars a yearMixed use (base case)304 thousand dollars a yearService or medical53 thousand dollars a year

In the base case the Town takes in $351,127 a year against $47,235 in costs, $41,293 of them General Fund, for a net of $303,892, or $5.63 per square foot. The retail-heavy case nets $453,173; the service-and-medical case nets $53,054, kept positive mainly by the required restaurant. "All scenarios remain positive under the current assumptions, but the range is wide," the analysis says, and it calls the base case "a transparent screening case" rather than a forecast. There is also a one-time construction use tax estimated at $321,300. The applicant's slide to council rounded the base case to "$304,000 annual net positive impact," which is the Finance Department's middle number presented without the other two. No new town-maintained lane miles are assumed, which is why the transportation line in the expense column is zero.

What the developer pays for

The development agreement puts the public improvements on the owner, in two forms. Before the first certificate of occupancy, the owner builds the signal modifications at the Ridge Road access, a 100-foot northbound left-turn lane and a 100-foot southbound right-turn lane, each with a 262-foot taper, and the eastbound approach with its own left-turn lane, and closes every other access to the property except the emergency one. The signal and turn-lane work is eligible for reimbursement under the agreement's reimbursement section.

At the first site construction permit the owner pays its share of four larger projects, pro-rated by the master traffic study and each capped: 2.3 percent of the Four Corners intersection project, up to $186,300; 0.004 percent of widening Highway 86 from Ridge Road to Enderud Boulevard, up to $8,240 plus inflation; 1.6 percent of widening Fifth Street from Woodlands Boulevard to Founders Parkway, up to $288,000 plus inflation; the Ridge Road frontage project, up to $612,737; and 100 percent of the Town's right-of-way acquisition costs for that frontage, up to $220,335, including appraisals and attorney fees. The caps add to about $1.316 million. There is no park site on the lot, so the 0.7-acre public-land requirement becomes cash in lieu, estimated at $9,148. The property leaves the Castle Rock Fire Protection District and is served by the Town's fire department; the owner funds a wildland-urban-interface assessment of the conveyed open space and files a fire protection plan before the first building permit.

The clock is the part council asked about. The agreement vests the plan through Dec. 31, 2036. By that date the owner must have spent at least $500,000 on public improvements and pulled the first commercial building permit, or the Town suspends further development rights, a suspension council can lift for good cause. Mayor Pro Tem Laura Cavey asked at first reading what happens at the ten-year mark and got that answer; Councilmember Kevin Bracken asked when the road contributions are paid, and was told at the site construction permit. There are no fee waivers in the agreement, no school or fire-station land, and no interchange obligation.

How it got here with eight people watching

The petition was accepted in September 2023 and filed with the clerk that November. Council found it in substantial compliance on Dec. 19, 2023, and eligible on Feb. 6, 2024; the eligibility report puts the perimeter at 3,426.30 feet, of which 2,740 feet, or 80 percent, touches the town, against the one-sixth state law requires, and every private owner signed, so no election was needed. The annexation ordinance itself recites that town code calls for the hearing within 180 days of the eligibility finding; the hearing came 32 months later, and nothing we read explains the gap, so we do not know how it was handled.

The applicant held three neighborhood meetings. The first, in July 2023, drew six residents. The second, in April 2025 at Cantril School, drew nobody; the summary records "Questions Presented to Applicant: None." The third, on Sept. 28 of this year, drew two, who asked about height, the Ridge Road work, the restaurant, whether there would be housing, what "town center" means, tenants, access and soils. One written comment is in the file, an email from July 2023 from a 23-year resident of 80104 opposing the project: "the growth is out of control," the notice sign was posted inside a construction zone where nobody saw it, and Ridge Road was being widened for today's traffic, not a shopping plaza. The Planning Commission recommended approval 5-0 on Oct. 8. On Oct. 20, Tara Vargish presented all three ordinances, the applicant presented, Councilmember Mark Davis confirmed the westbound left-turn lane, Councilmember Max Brooks asked about the uses and the drive-through, and the minutes note reads, in full, "No public comments."

No public comments.

For scale, the town's recent annexations run from Pine Canyon's 533 acres across I-25, vested through 2050, and the Town's own 681-acre Lost Canyon Ranch, down to the 5-acre Memmen parcel next door in 2023 and a 4.7-acre add-on to Dawson Trails this year. RidgeView, at 10.54 acres including 0.36 acres of the Town's own Ridge Road right-of-way, is among the smallest private annexations of the period. The staff report also notes, in passing, that the intergovernmental development plan between Castle Rock and Douglas County, the agreement that once governed annexations at the town's edge, "expired several years ago and has not been renewed."

Election night

Council's Nov. 3 agenda was not posted when we checked Thursday; the three RidgeView ordinances carry that date in the town's records as second readings, and the regular meeting time is 6 p.m. at Town Hall, 100 N. Wilcox St. Written comments go to CRgov.com/CouncilComments by 1 p.m. on meeting day, and the meeting streams at CRgov.com/WatchCouncil. Three of the seven seats at that table, the mayor's and Districts 3 and 5, are on the ballot that closes an hour later; the mayor's race and the council districts are here, and the growth-and-water question that runs through both is the question this file answers in miniature.

Next edition around Nov. 12. Tips, corrections and site photos to hello@discoverdougco.com.

Local DougCo news worth your inbox

We dig into the Douglas County stories — elections, development, what's opening — that the big outlets skip. Free, no spam.

No spam. Unsubscribe anytime.

Comments

Sign in with Google to comment

Loading comments…